Pre-Construction Work Begins for New Roundabout
February 6, 2025 – Preliminary work for a new roundabout at Pleasant Valley Road and 39th Avenue is set to begin next week.
![Vernon Gets New Roundabout](https://static.wixstatic.com/media/e30afb_2db96ad8ce0e48c89c67915e5fa1dfe5~mv2.jpg/v1/fill/w_980,h_532,al_c,q_85,usm_0.66_1.00_0.01,enc_auto/e30afb_2db96ad8ce0e48c89c67915e5fa1dfe5~mv2.jpg)
Timeline:
February 10-21, 2025 – BC Hydro crews relocate utility poles. Traffic will be reduced to a single alternating lane, causing minor delays. Drivers should use caution and give space to roadside workers.
March 2025 – Full roundabout construction begins.
Fall 2025 – Project completion, including new street lighting, a pedestrian-controlled crosswalk, anti-skid pavement, and drainage improvements to enhance safety and traffic flow.